Greening a corporate campus is a project, not a purchase. A new headquarters or multi-building campus may need hundreds of floor plants, several statement trees, green walls across multiple floors and planting for cafés, lobbies and outdoor areas. Each element has its own design approvals, production times and installation constraints, and all of them have to fit within a construction or fit-out program. This guide explains how to manage large-scale artificial plant projects for corporate campuses, from the first brief to handover and long-term support.
Set up the project structure
Large planting projects involve many stakeholders: workplace strategy, interior designers, facilities, procurement, fire engineers, main contractors and the supplier. Confusion over responsibilities is the most common cause of delay. Before ordering, agree on:
- A single project owner on the client side who approves designs and changes;
- A named contact at the supplier responsible for production and shipping updates;
- Who installs: the supplier, a specialist installer, the fit-out contractor or the facilities team;
- Approval gates for design, samples, documentation and pre-shipment inspection;
- A change process for late design revisions, with clear effects on cost and time.
Translate the design into a bill of quantities
Designers usually present greenery in renders and mood boards. Production needs something more precise. Convert the design into a bill of quantities that lists every item with:
- a unique reference code tied to the drawing;
- dimensions, including height, spread and planter size;
- material and finish specifications, including UV-resistant or fire-retardant requirements;
- quantity per building, floor and zone;
- delivery address and required on-site date.
Separate standard catalog items from custom pieces, because they follow different timelines. Custom trees, bespoke panels and branded installations need design development and sampling, while standard plants can often move straight to production once quantities are confirmed. At Sharetrade, custom design from drawings or references is provided free of charge, and molds and materials are developed in-house.
Sampling and approvals
Sampling protects the project from costly surprises. Plan a sampling round for every custom item and for any standard item that will be used in large numbers:
- request stock samples early to confirm the general palette;
- allow time for custom samples, typically around 10 working days at Sharetrade, plus shipping;
- review samples in the actual building or a mock-up under the planned lighting;
- share fire and material documentation with the fire engineer at the same time;
- record approvals formally and retain approved samples as the reference for production.
For very large statement trees, a full-size sample is rarely practical. Instead, approve a branch section, leaf samples and trunk finish, supported by drawings and progress photographs from the factory.
Production planning and capacity
Large campus orders can represent a significant share of a supplier's monthly output, so confirm capacity before committing to dates. Ask the supplier to provide a production schedule split by item, and identify which items sit on the critical path. Statement trees and custom panels usually take longest; standard floor plants can be scheduled to complete in time for the same shipment.
Production lead times typically range from 15 to 45 days at Sharetrade depending on design and quantity, with capacity of around 30,000 plants per month. Add shipping, customs clearance and inland delivery to determine when production must start. Build in contingency for design changes and inspection.
Shipping and phased delivery
Campus projects rarely receive everything at once. Buildings are completed in sequence, floors are handed over at different times and storage on site is limited. Plan logistics around the construction program:
- Phase shipments to match building or floor handovers, using FCL where volumes justify full containers and LCL for smaller phases;
- Label by destination, with building, floor and zone on every carton, so goods go directly to the right place;
- Use detachable designs for large trees to reduce carton volume and fit through doors and lifts;
- Specify drop-tested packaging to minimize damage during handling on site;
- Reserve air freight for urgent replacements or late additions;
- Arrange inspection before goods leave the factory, against approved samples.
Check site logistics early: loading bay access, lift dimensions and weight limits, delivery time windows and whether a temporary storage area is available.
Installation and handover
Installation should be scheduled after dusty trades are finished but before final cleaning and occupation. Provide installers with drawings, the bill of quantities, assembly guides and photographs of approved samples. For high-level features, coordinate access equipment and any permits needed for working at height.
At handover, the facilities team should receive a complete package:
- an asset schedule listing every item by location and reference code;
- fire test reports and material documentation for the installed products;
- cleaning and maintenance guidance;
- contact details and reorder references for replacements;
- photographs of each completed zone.
Supporting the campus after occupation
Once people move in, needs change. Teams relocate, meeting rooms are repurposed and new amenity spaces open. Plan for this by ordering a small stock of spare high-wear items, agreeing how long the supplier will retain molds and specifications, and reviewing planting condition annually. A clear asset register makes it simple to move plants between buildings rather than buying new ones.
Conclusion
Large-scale artificial plant projects succeed when they are run with the same discipline as any other fit-out package. Define roles, translate designs into precise quantities, sample and approve carefully, confirm production capacity, phase shipping to match the construction program and hand over complete records. Managed this way, campus greenery arrives on time, matches the design intent and remains easy to maintain for years.