Installing large artificial trees on site is a logistics exercise as much as a landscaping one. A five or six metre statement tree for a hotel atrium or airport concourse arrives in multiple cartons, has to pass through doorways and lifts designed for people, and must be assembled, anchored and shaped in a space where other trades are still finishing. Contractors who plan the installation of large artificial trees before the order is placed avoid the most common problems: pieces that will not fit through access routes, missing fixings and trees that look flat because there was no time to shape them.
Survey the access route before you order
The tree has to get from the delivery vehicle to its final position. Walk the route and record the tightest points:
- Loading bay height and any restrictions on vehicle size or delivery hours.
- Door widths and heights, including temporary hoardings and protection.
- Goods lift internal dimensions, door opening and load capacity.
- Corridor turns, where long trunk sections may not get around a corner.
- Floor loading limits along the route and at the final position.
- Finished surfaces that need protection, such as stone flooring or glazing.
Share these dimensions with the manufacturer. They determine how the tree is split into sections, which affects both design and packaging.
Detachable design and packaging
Large artificial trees are normally made in sections: a trunk, sometimes split into two or more lengths, and a set of branches that plug or bolt into sockets on the trunk. This detachable design reduces carton volume, which lowers freight cost and makes handling on site realistic. Sharetrade builds large statement trees to measure and uses detachable designs with drop-tested packaging, so the pieces arrive protected and in manageable sizes.
Before shipping, ask for:
- A packing list showing every carton, its dimensions and gross weight.
- Branch numbering that matches socket numbering on the trunk.
- Assembly drawings or photographs of the completed tree from several angles.
- A list of included fixings and tools, and which items you need to supply locally.
Cartons should be labelled by tree and by position if the project has several large trees, so the right pieces reach the right location.
Delivery, storage and sequencing
Coordinate delivery with the main contractor's logistics plan. On busy sites, delivery slots are limited and storage is scarce.
- Timing: deliver as close to installation as practical. Long storage in a dusty, crowded area risks damage and lost cartons.
- Storage: if storage is unavoidable, keep cartons dry, flat and away from welding, cutting and painting work.
- Sequencing: install after ceilings, lighting and major floor finishes are complete in the area, but before final cleaning.
- Freight planning: lead times typically range from 15 to 45 days at the factory, plus sea or air freight. Build this into the procurement programme so delivery is not squeezed against handover.
Lifting, assembly and anchoring
Assembly method depends on the tree's size and the space available. Plan the following in advance:
Lifting equipment
Heavy trunk sections may need a gantry, chain hoist, material lift or small crane. Check the ceiling for suitable lifting points only with the structural engineer's approval. Mobile access towers or scissor lifts are usually needed for upper branches. Include all equipment in your method statement and risk assessment.
Assembly order
Typically the trunk is set and fixed first, then branches are inserted from the bottom up, working around the tree. Following the numbering avoids having to remove branches later. Keep a second person at ground level to check the canopy shape from normal viewing positions.
Anchoring and base
Large trees must be stable against accidental impact and, in some locations, vibration or air movement. Common solutions include a steel base plate bolted to the slab, a ballasted base within the planter, or a sleeve cast into the planter structure. The anchoring design should be confirmed with the structural engineer, especially for tall trees in public areas. Once fixed, the planter is usually topped with decorative stone, bark or moss to conceal the base.
Shaping and finishing
Branches and leaves are compressed for transport. Shaping, sometimes called fluffing, is what turns a set of parts into a convincing tree. Allow realistic labour time for it.
- Open each branch and spread leaf clusters so the canopy has depth rather than flat layers.
- Adjust branch angles to fill gaps seen from main sightlines, entrances and upper floors.
- Check clearances to sprinkler heads, lighting, signage and handrails.
- Remove packaging debris, dust the leaves and clean the planter top.
- Photograph the finished tree for the handover file and as a reference for future maintenance.
Safety and method statements
Large tree installations involve work at height, heavy lifting and work in occupied or near-complete spaces. Your method statement should cover the lifting plan, access equipment, exclusion zones, protection of finishes and the sequence of assembly. If the building is occupied, agree working hours and barriers with the facility manager. Confirm that any fire performance requirement for the tree has been addressed before installation, and keep the supplier's test reports with the handover documentation where applicable.
Conclusion
A large artificial tree is easiest to install when its sections, packaging and assembly method are designed around the site from the start. Survey the access route, share the dimensions with the manufacturer, plan delivery and lifting carefully, and allow real time for shaping. Done that way, the installation is a short, controlled operation and the finished tree matches the design intent on the drawings.